Projects
HomeProjects
Completed Projects
Nadiad Petlad Khambhat from 9/00 km to 51/600 km
A. Part I
- Project Start Date: 27/03/2017
- Project Cost: 7.44
- Chainage: 34/800 to 51/600
- Project Completion: 5/10/2017
- Work Detail: Resurfacing
- Client: R & B Department Anand
- Project Start Date: 01/03/2014
- Project Cost: 14.56
- Chainage: 9/00 to 34/800
- Project Completion: 18/05/2015
- Work Detail: Widening from 7 M to 10 M
- Client: R & B Department Anand
Issarwada Sath Jalundh
- Project Start Date: 06/03/2019
- Project Cost: 7.56 Cr.
- Chainage: Km. 0/0 to 18/200
- Project Completion Date: 01/06/2019
- Work Detail: Resurfacing
- Client: R & B Department Anand
Anand Bhalej Lingda
- Project Start Date: 02/10/2017
- Project Cost: 26.49 Cr.
- Chainage: Km. 0/0 to 19/200
- Project Completion Date: 13/12/2018
- Work Detail:Widening from 7 M to Four Lane
- Client: R & B Department Anand
Bhalej Ode Ahima
- Project Start Date: 23/10/2019
- Project Cost: 12.98 Cr.
- Chainage: Km. 0/0 to 14/700
- Project Completion Date: 15/10/2020
- Work Detail: Widening from 7.00 M to 10.00 M
- Client: R & B Department Anand
Bhalej Sarsa Road
- Project Start Date: 23/10/2017
- Project Cost: 10.18 Cr.
- Chainage: Km. 6/00 to 15/600
- Project Completion Date: 8/8/2018
- Work Detail: Widening from 7 M to 10 M
- Client: R & B Panchayat Department Anand
Borsad Bhadran Kinkhlod Gambhira
- Project Start Date: 05/09/2019
- Project Cost: 20.41 Cr.
- Chainage: Km. 35/800 to 56/070
- Project Completion Date: 20/8/2020
- Work Detail: Widening from 7.00 M to 10.00 M
- Client: R & B Department Anand
Dandi Path from Bhumel to Nadiad
- Project Start Date: 04/06/2018
- Project Cost: 19.27 Cr.
- Chainage: Km. 71/200 to 77/600
- Project Completion Date: 28/04/2019
- Work Detail: Widening from 7.00 M to Four Lane
- Client: National Highway Division, Vadodara
Vadtal Jol Bakrol
- Project Start Date: 15/01/2020
- Project Cost: 4.03 Cr.
- Chainage: Km. 0/0 to 9/100
- Project Completion Date: 10/03/2020
- Work Detail: Resurfacing
- Client: R & B Department Anand
Dandi Path in Borsad
- Project Start Date: 25/02/2019
- Project Cost: 1.84 Cr.
- Chainage: Km. 104/920 to 106/670 & 122/870 to 127/400
- Project Completion Date: 18/05/2019
- Work Detail: Resurfacing
- Client: R & B Department Anand
1) Nadiad Petlad Khambhat from 9/00 km to 51/600 km
A. Part I
- Project Start Date: 27/03/2017
- Project Cost: 7.44
- Chainage: 34/800 to 51/600
- Project Completion: 5/10/2017
- Work Detail: Resurfacing
- Client: R & B Department Anand
- Project Start Date: 01/03/2014
- Project Cost: 14.56
- Chainage: 9/00 to 34/800
- Project Completion: 18/05/2015
- Work Detail: Widening from 7 M to 10 M
- Client: R & B Department Anand
2) Issarwada Sath Jalundh
- Project Start Date: 06/03/2019
- Project Cost: 7.56 Cr.
- Chainage: Km. 0/0 to 18/200
- Project Completion Date: 01/06/2019
- Work Detail: Resurfacing
- Client: R & B Department Anand
3)Anand Bhalej Lingda
- Project Start Date: 02/10/2017
- Project Cost: 26.49 Cr.
- Chainage: Km. 0/0 to 19/200
- Project Completion Date: 13/12/2018
- Work Detail:Widening from 7 M to Four Lane
- Client: R & B Department Anand
4) Bhalej Ode Ahima
- Project Start Date: 23/10/2019
- Project Cost: 12.98 Cr.
- Chainage: Km. 0/0 to 14/700
- Project Completion Date: 15/10/2020
- Work Detail: Widening from 7.00 M to 10.00 M
- Client: R & B Department Anand
5) Bhalej Sarsa Road
- Project Start Date: 23/10/2017
- Project Cost: 10.18 Cr.
- Chainage: Km. 6/00 to 15/600
- Project Completion Date: 8/8/2018
- Work Detail: Widening from 7 M to 10 M
- Client: R & B Panchayat Department Anand
6) Borsad Bhadran Kinkhlod Gambhira
- Project Start Date: 05/09/2019
- Project Cost: 20.41 Cr.
- Chainage: Km. 35/800 to 56/070
- Project Completion Date: 20/8/2020
- Work Detail: Widening from 7.00 M to 10.00 M
- Client: R & B Department Anand
7) Dandi Path from Bhumel to Nadiad
- Project Start Date: 05/09/2019
- Project Cost: 20.41 Cr.
- Chainage: Km. 35/800 to 56/070
- Project Completion Date: 20/8/2020
- Work Detail: Widening from 7.00 M to 10.00 M
- Client: R & B Department Anand
8) Vadtal Jol Bakrol
- Project Start Date: 15/01/2020
- Project Cost: 4.03 Cr.
- Chainage: Km. 0/0 to 9/100
- Project Completion Date: 10/03/2020
- Work Detail: Resurfacing
- Client: R & B Department Anand
9) Dandi Path in Borsad
- Project Start Date: 25/02/2019
- Project Cost: 1.84 Cr.
- Chainage: Km. 104/920 to 106/670 & 122/870 to 127/400
- Project Completion Date: 18/05/2019
- Work Detail: Resurfacing
- Client: R & B Department Anand
Ongoing Projects
Strom Water Drain at Anand
- Project Start Date:
- Project Cost:
- Chainage:
- Time Limit:
- Work Detail:
- Client: Nagar Palika, Anand
PMGSY from Shilli to Malsarpura (Dist: Anand)
- Project Start Date: 25/09/2020
- Project Cost: 5.65 Cr.
- Chainage: Km. 0/0 to 10/600
- Time Limit: 18 Months
- Work Detail: Widening from 3.75 M to 5.50 M
- Client: R & B Panchayat Department Anand
PMGSY from Shekhupur to Chanor/Indraverna (Dist: Kheda)
- Project Start Date: 26/10/2020
- Project Cost: 5.42 Cr.
- Chainage: Km. 0/0 to 6/960 & 0/0 to 5/800
- Time Limit: 18 Months
- Work Detail: Widening from 3.75 M to 5.50 M
- Client: R & B Panchayat Department Anand